LLC “BR-Wood” proceed with the construction of new organization for lumber and wood pellets production.

After important stage of site preparation, included significant dismantling and and exploration operations , temporary electricity lines construction, the reconstruction of the future lumber yard buildings and pellet plant were initiated on the “BR-Wood” stage.

3_1.jpg














. Since November 2020, the equipment supply for the sawmill shop with a processing volume of 197,000 m3 of sawlog per year has begun. The supplier of equipment and technology is the leading Swedish company USNR. Since April 2021, the first machines with the equipment of the Katres drying chamber complex, which is capable drying up to 100,000 m3 of lumber per year, have been accepted. Boiler equipment with a total capacity of 9 MW was purchased.